Construction on the Schoharie Fire Stations is progressing with excellent workmanship and results.
  • The foundations, structural steel framing and CMU block walls are complete
  • Work on the exterior ashlar pattern block veneer is at about 85% completion
  • Windows are getting ready for installation
  • Interior framing is at 95% completion and the Roof truss framing is also nearing completion
Coming in the next month
  • Completion of the exterior block veneer
  • Installation of the Apparatus Bay Section Overhead Doors
  • Completion of all project windows
  • Start of standing seam metal roof system
  • Start of interior gypsum wallboard installation
  • Continued progress on interior building plumbing, mechanical, electrical and fire suppression work
  • Completion of National Grid incoming Electrical Services
  • Start of exterior soffit and fascia work